Installing is as simple as installing any other type of basic wall panelling.

A basic 15 foot wall (2 wainscot sections) with 2 receptacles could take as little as an hour to install.

  • First, pre-fit sections and measure for final trimming
  • Trim ends and cutouts for windows, vents, etc.
  • Screw or nail sections to the prepared wall where studs are located
  • Fill as needed and lightly sand
  • Apply desired finish coat
  • Enjoy for years to come!

IntriG Wainscot is shipped pre-primed and includes:

  • Approximately 1/2” extra material on the end of each section that meets a corner
  • Tongue-in-groove edges that connect multiple sections in a run
  • Reverse molding to use where needed for receptacles, ducts and other minor obstructions
  • Unique, detailed Installation Instructions
  • Part Labels on reverse side of each section 
  • Cap and Cap Mold